Timesheet 2004:

Builder Name: Kevin Wilkerson   Project to date totals
Project: Rans S-6S Coyote II - Received kit on 12/10/2002  
E-mail: kevinw@perfhyd.com   Total Hours 2004: 266.50
Phone: (812) 479-7831   Carried Forward From 2003: 416.00
Other: (812) 455-7942 - Cell   Total Hours to Date: 682.50
January, February, March
Jan-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday                    
Tuesday                    
Wednesday             2.00 Open Aft Baggage fabric area; prep for tapes    
Thursday                    
Friday 1.50 Drill antenna ground plane for COM and TXP antenna     2.00 Prep fuse for fabric, iron edges 1.50 Prep Vertical Stabilizer fot edge tapes    
Saturday 6.00 Attach bottom fabric sheet on fuselage 6.50 Apply fabric to left side of fuselage 7.00 Apply fabric to right side, shrink fuselage to final 6.50 Prep for edge tape; rib rivet vertical stabilizer; edge tape tail section 5.50 Tape and patches on fuselage
Sunday 1.50 Prefit fabric to left side of fuselage                
Total weekly hours 9.00   6.50   9.00   10.00   5.50  
                     
Jan. total hours 40.00                  
                     
                     
Feb-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday                    
Tuesday                    
Wednesday                    
Thursday                    
Friday 2.00 Tape top left and both side stringers                
Saturday 4.50 Tape both bottom longerons, fwd formers, S3 top  3.00 Complete fabric application!     4.00 Move fuse to paintshop, start panel    
Sunday 4.00 Tape door frames, firewall, horizontal stabilizer patches, drill aft access cover 3.00 Complete edge checking, etc.      2.50 Work on panel items    
Total weekly hours 10.50   6.00   0.00   6.50   0.00  
                     
Feb. total hours: 23.00                  
                     
                     
Mar-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday 2.50 Work on panel items                
Tuesday                    
Wednesday 1.00 Work on panel items                
Thursday                    
Friday 1.50 Paint shop                
Saturday 3.00 Paint shop and panel items 5.00 Work at hangar, work on panel 4.50 Finish panel cutouts, map box 7.00 Move STUFF to hangar    
Sunday 5.00 Check fabric edges, move fuselage to hangar 2.00 Install rudder & steering horns, rivet map box     5.00 Move wings to hangar, finish moving 'other stuff' to hangar.    
Total weekly hours 13.00   7.00   4.50   12.00   0.00  
                     
Mar. total hours: 36.50                  
                     
April, May, June
Apr-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday                    
Tuesday                    
Wednesday                    
Thursday                    
Friday     4.00 Pick up remaining painted items, trim cable            
Saturday 6.00 Begin final assembly     7.00 Continue final assembly 7.00 Continue final assembly    
Sunday 4.00 Rudder cables, tailwheel chain & spring assy                
Total weekly hours 10.00   4.00   7.00   7.00   0.00  
                     
Apr. total hours: 28.00                  
                     
                     
                     
May-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday             2.50 Install COM Antenna & Light Assemblies    
Tuesday 2.50 Pick up and deliver engine         7.50 Install brake lines, etc.    
Wednesday                    
Thursday             6.50 Ailerons & Flaps    
Friday             6.00 Gap seals - left wing    
Saturday 6.00 Final assembly continues     2.00 Take doors to paint shop        
Sunday         1.00 Start on Strobe PS 5.00 Install Strobe PS, ELT, Antennas    
Total weekly hours 8.50   0.00   3.00   27.50   0.00  
                     
May total hours: 39.00                  
                     
                     
                     
Jun-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday                    
Tuesday                    
Wednesday                    
Thursday                    
Friday                    
Saturday 6.50 Panel items, set up and hang wings 8.00 Final assy con't 3.50 Doors, panel items        
Sunday                    
Total weekly hours 6.50   8.00   3.50   0.00   0.00  
                     
June total hours: 18.00                  
                     
                     
July, August, September
Jul-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday                    
Tuesday                    
Wednesday                    
Thursday                    
Friday                    
Saturday                    
Sunday                 7.00 Aft lift struts rig flaps
Total weekly hours 0.00   0.00   0.00   0.00   7.00  
                     
July total hours: 7.00                  
                     
                     
                     
Aug-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday                    
Tuesday                    
Wednesday                    
Thursday                    
Friday                    
Saturday 4.50 Flap & Aileron Closeouts, begin wiring     6.00 PTT Wiring, Panel wiring 4.50 Wiring, antenna cables    
Sunday                    
Total weekly hours 4.50   0.00   6.00   4.50   0.00  
                     
Aug. total hours: 15.00                  
                     
                     
                     
Sep-04 Week 1 Work Area Week 2 Work Area Week 3 Work Area Week 4 Work Area Week 5 Work Area
Monday