Builder Name: |
Kevin Wilkerson |
|
Project to date totals |
|
Project: |
Rans S-6S Coyote II - Received kit on 12/10/2002 |
|
|
E-mail: |
kevinw@perfhyd.com |
|
Total Hours 2004: |
266.50 |
|
Phone: |
(812) 479-7831 |
|
Carried Forward From 2003: |
416.00 |
|
Other: |
(812) 455-7942 - Cell |
|
Total Hours to Date: |
682.50 |
|
January, February, March |
|
Jan-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|
|
|
|
|
|
Tuesday |
|
|
|
|
|
|
|
|
|
|
|
Wednesday |
|
|
|
|
|
|
2.00 |
Open Aft Baggage fabric area; prep for tapes |
|
|
|
Thursday |
|
|
|
|
|
|
|
|
|
|
|
Friday |
1.50 |
Drill antenna ground plane for COM and TXP antenna |
|
|
2.00 |
Prep fuse for fabric, iron edges |
1.50 |
Prep Vertical Stabilizer fot edge tapes |
|
|
|
Saturday |
6.00 |
Attach bottom fabric sheet on fuselage |
6.50 |
Apply fabric to left side of fuselage |
7.00 |
Apply fabric to right side, shrink fuselage to final |
6.50 |
Prep for edge tape; rib rivet vertical stabilizer; edge tape tail
section |
5.50 |
Tape and patches on fuselage |
|
Sunday |
1.50 |
Prefit fabric to left side of fuselage |
|
|
|
|
|
|
|
|
|
Total weekly hours |
9.00 |
|
6.50 |
|
9.00 |
|
10.00 |
|
5.50 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Jan. total hours |
40.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Feb-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|
|
|
|
|
|
Tuesday |
|
|
|
|
|
|
|
|
|
|
|
Wednesday |
|
|
|
|
|
|
|
|
|
|
|
Thursday |
|
|
|
|
|
|
|
|
|
|
|
Friday |
2.00 |
Tape top left and both side stringers |
|
|
|
|
|
|
|
|
|
Saturday |
4.50 |
Tape both bottom longerons, fwd formers, S3 top |
3.00 |
Complete fabric application! |
|
|
4.00 |
Move fuse to paintshop, start panel |
|
|
|
Sunday |
4.00 |
Tape door frames, firewall, horizontal stabilizer patches, drill aft
access cover |
3.00 |
Complete edge checking, etc. |
|
|
2.50 |
Work on panel items |
|
|
|
Total weekly hours |
10.50 |
|
6.00 |
|
0.00 |
|
6.50 |
|
0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Feb. total hours: |
23.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Mar-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
2.50 |
Work on panel items |
|
|
|
|
|
|
|
|
|
Tuesday |
|
|
|
|
|
|
|
|
|
|
|
Wednesday |
1.00 |
Work on panel items |
|
|
|
|
|
|
|
|
|
Thursday |
|
|
|
|
|
|
|
|
|
|
|
Friday |
1.50 |
Paint shop |
|
|
|
|
|
|
|
|
|
Saturday |
3.00 |
Paint shop and panel items |
5.00 |
Work at hangar, work on panel |
4.50 |
Finish panel cutouts, map box |
7.00 |
Move STUFF to hangar |
|
|
|
Sunday |
5.00 |
Check fabric edges, move fuselage to hangar |
2.00 |
Install rudder & steering horns, rivet map box |
|
|
5.00 |
Move wings to hangar, finish moving 'other stuff' to hangar. |
|
|
|
Total weekly hours |
13.00 |
|
7.00 |
|
4.50 |
|
12.00 |
|
0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mar. total hours: |
36.50 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
April, May, June |
|
Apr-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|
|
|
|
|
|
Tuesday |
|
|
|
|
|
|
|
|
|
|
|
Wednesday |
|
|
|
|
|
|
|
|
|
|
|
Thursday |
|
|
|
|
|
|
|
|
|
|
|
Friday |
|
|
4.00 |
Pick up remaining painted items, trim cable |
|
|
|
|
|
|
|
Saturday |
6.00 |
Begin final assembly |
|
|
7.00 |
Continue final assembly |
7.00 |
Continue final assembly |
|
|
|
Sunday |
4.00 |
Rudder cables, tailwheel chain & spring assy |
|
|
|
|
|
|
|
|
|
Total weekly hours |
10.00 |
|
4.00 |
|
7.00 |
|
7.00 |
|
0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Apr. total hours: |
28.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
May-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|
2.50 |
Install COM Antenna & Light Assemblies |
|
|
|
Tuesday |
2.50 |
Pick up and deliver engine |
|
|
|
|
7.50 |
Install brake lines, etc. |
|
|
|
Wednesday |
|
|
|
|
|
|
|
|
|
|
|
Thursday |
|
|
|
|
|
|
6.50 |
Ailerons & Flaps |
|
|
|
Friday |
|
|
|
|
|
|
6.00 |
Gap seals - left wing |
|
|
|
Saturday |
6.00 |
Final assembly continues |
|
|
2.00 |
Take doors to paint shop |
|
|
|
|
|
Sunday |
|
|
|
|
1.00 |
Start on Strobe PS |
5.00 |
Install Strobe PS, ELT, Antennas |
|
|
|
Total weekly hours |
8.50 |
|
0.00 |
|
3.00 |
|
27.50 |
|
0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
May total hours: |
39.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Jun-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|
|
|
|
|
|
Tuesday |
|
|
|
|
|
|
|
|
|
|
|
Wednesday |
|
|
|
|
|
|
|
|
|
|
|
Thursday |
|
|
|
|
|
|
|
|
|
|
|
Friday |
|
|
|
|
|
|
|
|
|
|
|
Saturday |
6.50 |
Panel items, set up and hang wings |
8.00 |
Final assy con't |
3.50 |
Doors, panel items |
|
|
|
|
|
Sunday |
|
|
|
|
|
|
|
|
|
|
|
Total weekly hours |
6.50 |
|
8.00 |
|
3.50 |
|
0.00 |
|
0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
June total hours: |
18.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
July, August, September |
|
Jul-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|
|
|
|
|
|
Tuesday |
|
|
|
|
|
|
|
|
|
|
|
Wednesday |
|
|
|
|
|
|
|
|
|
|
|
Thursday |
|
|
|
|
|
|
|
|
|
|
|
Friday |
|
|
|
|
|
|
|
|
|
|
|
Saturday |
|
|
|
|
|
|
|
|
|
|
|
Sunday |
|
|
|
|
|
|
|
|
7.00 |
Aft lift struts rig flaps |
|
Total weekly hours |
0.00 |
|
0.00 |
|
0.00 |
|
0.00 |
|
7.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
July total hours: |
7.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Aug-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|
|
|
|
|
|
Tuesday |
|
|
|
|
|
|
|
|
|
|
|
Wednesday |
|
|
|
|
|
|
|
|
|
|
|
Thursday |
|
|
|
|
|
|
|
|
|
|
|
Friday |
|
|
|
|
|
|
|
|
|
|
|
Saturday |
4.50 |
Flap & Aileron Closeouts, begin wiring |
|
|
6.00 |
PTT Wiring, Panel wiring |
4.50 |
Wiring, antenna cables |
|
|
|
Sunday |
|
|
|
|
|
|
|
|
|
|
|
Total weekly hours |
4.50 |
|
0.00 |
|
6.00 |
|
4.50 |
|
0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Aug. total hours: |
15.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
Sep-04 |
Week 1 |
Work Area |
Week 2 |
Work Area |
Week 3 |
Work Area |
Week 4 |
Work Area |
Week 5 |
Work Area |
|
Monday |
|
|
|
|
|
|