12/11/02 - First day in the shop |
12/12/02 - Inventory Begins! |
12/14/02 - Parts Count...part 2 |
|
12/21/02 - Inventory finished,
building begins! |
12/28/02 & 12/29/02 - Assembling floorboard
components |
01/01/03 - Pre-fit, drill and cleco
firewall and cowl mounting brackets. Drill upper engine mount. |
|
01/03/03 - Fit, clamp, drill & rivet
right side fwd contour former |
01/04/03 - Fit, clamp, drill & rivet
left side fwd contour former and begin work on control stick assembly |
01/05/03 - Complete control stick
assembly installation, assemble and install Aileron Cable assembly |
|
01/08/03 - Fabricate stops &
bushings, assemble and install Elevator Push-Pull Tube Assembly |
01/15/03 - Begin trim and fit
interior sections (Ugh! - Well at first, but all's well that ends
well!) |
01/18/03 - Complete interior pre-fit,
start seat construction and assembly |
|
02/04/03 - Finally back to work!
Complete first seat and begin installing covers |
02/08/03 - Complete seat #1 covering, assemble seat #2 |
02/09/03 - Finish assy/cover 2nd
seat. Pre-fit finished, remove seats & interior, various minor items
fixed. |
|
02/15/03 - Assembled and installed the GEAR! Yes, of course
I sat in it! |
02/22/03 - Cut and fit windshield deck, panel top covers,
pre-fit panel. |
02/23/03 - Completed panel top closeouts and final pre-fit
instrument panel. |
|
03/01/03 - Built gear-jig,
pre-fit, drilled and installed main gearlegs. Built traveler for
moving fuse in-shop. |
03/08/03 - Fit, drill and cut axles, finish cut windshield
deck. |
03/12/03 - Remove panel top
closeouts, remove wheels and main gear, reinstall windshield deck,
initial layout, drill and cleco windshield to S2 tabs. |
|
03/15/03 - Finish trim deck,
fit, drill and trim windshield, reinstall gear and wheels. |
03/16
- 03/17 - 03/22/03 - Working on door construction and assembly. |
03/23/03 - Finish trim right
side door window. Fit, trim, drill, cleco and reinstall left
side door/window assembly. |
|
03/24/03 -
Fabricate & install battery box. |
03/29/03 - Install Aft Baggage
Compartment, drill & cleco frame, etc. |
04/02 - 04/05/03 - Working on
right side replacement bubble door installation. |
|
04/11 - 04/12/03 - Working on
left side replacement bubble door installation. |
04/13/03 - Finished left side
door assembly and completed the first phase of my project!!! |
04/14/03 - Begin work on
vertical stabilizer. |
|
04/16/03 - Fabricate patch for
aft baggage compartment frame, drill door and install quick locks,
hang rudder. |
04/17/03 - Finish aft baggage
compartment frame, rivet door hinges. Construct left & right
horizontal stabilizers. |
04/18/03 - Install compression
ribs in horizontal stabilizers, install hardware on elevators and
attach all to tail group. |
|
04/19/03 - Install rudder cap,
rudder horns and hardware, fabricate and install trim tab. |
04/20/03 - Happy Easter! -
Installed cables on tail group, installed elevator push/pull tube and
yoke, second phase of project nearly complete!!! |
04/21/03 - Adjust elevator
up/down position and installed elevator stops. |
|
04/26/03 - Install doubler in
bottom rudder tube, assemble hardware on flaps & ailerons. |
05/03 - 05/06/03 - Rearrange
workspace, pull parts for wing construction. |
05/08 - 05/10/03 - Begin work on
wings, install hardware up to flap/aileron hinges. |
|
05/11/03 - Install flap &
aileron hinges, install internal bracing tubes on RH wing structure. |
05/14 - 05/17/03 - Install
internal brace tubes, left wing. Install Aileron Push Pull Tube
guides, L&R, Flap Teleflex Retainer L&R, Aileron Bell Crank Gusset and
Aileron Bell Crank L&R, L&R Wing Tip Bows. |
05/21 -22 - 05/23/03 - Working
on fuel tanks, pull parts, drill holes, install fittings, perform air
test. |
|
05/24/03 - Water test fuel
tanks, empty & clean tanks. Install tank support tubes and
hardware, install left side tank. |
05/25 - 05/26/03 - Drill & cleco
rib clips (fore & aft) on right side wing structure. |
05/27 - 28 - 29 - 05/31/03 -
Drill & cleco fore & aft rib clips on left wing structure. Drill
& cleco all topside ribs on left wing structure. - OUT OF CLECOS! |
|
06/07/03 - Drill & cleco all
remaining top and bottom ribs in Left and Right Wing structures. - OUT
OF CLECOS AGAIN! |
06/14/03 - Drill & cleco root
rib skin and trim, drill & rivet rib channels for right side wing
structure. |
06/28/03 - Trim, drill, install
rib channels in right side wing structure. |
|
06/29/03 - Drill & rivet rib
clips on right side wing structure. |
07/02/03 - Finish drill & rivet
rib clips, rivet ribs to spars on right side wing structure. |
07/04 - 07/05/03 - Install rib
channels, drill & rivet rib ends and clips, install leading edge wrap on left side
wing structure. |
|
07/12/03 - Install leading edge
wrap and topside root skin on right side wing structure. |
07/13/03 - Rivet topside root
skin, drill & cleco fuel scupper. Trim, tension, drill & cleco
left side leading edge wrap. |
07/16 - 07/19/03 - Install top
and bottom root skins on left wing, epoxy-bond bottom side skin, begin
installation for antenna ground plane. |
|
07/20/03 - Install bottom root
skin on right wing, drill, rivet & epoxy-bond. Install antenna
mount plate. |
07/23 - 07/26/03 - Bond AND
rebond top aft skin on right wing, install braces on left wing from
rib 6 through 9, drill for pitot & static tubes. |
08/02/03 - Remove root rib
skins, cut left wing fuel tank neck to height, install Pitot & Static
tubes and lines, install left wing Nav/Strobe mount and wiring. |
|
08/03/03 - Right wing structure,
trim fuel tank neck to height, install wiring and tip mount for
Nav/Strobe kit, drill 5 ribs topside. |
08/4 - 08/09/03 - Finish drill &
debur top & bottom ribs on right wing. Drill & debur all ribs on
left wing. Install ends in aileron push pull tubes.
Install main push pull tube in left wing. Fabricate and install
flap lever assembly, flap teleflex cable & retainers, pre-install flap
teleflex cable in left wing. |
08/16/03 - Visited Rans factory
for the first time and ordered my kit ONE YEAR AGO TODAY! :^)
Rebonded left top aft and right bottom aft root wing skins today - no
fabric work today. :^( |
|
08/17/03 - Rivet LE Wrap L&R,
cut fabric for wings, remove tail section components for covering. |
08/23/03 - Fabric Covering Phase
Begins!!! Left horizontal stabilizer completed. |
08/30/03 - Cover right
horizontal stabilizer, cut fabric for elevators, rudder and one flap. |
|
|
|
|
|
08/31/03 - Cover left & right
elevators. |
09/06/03 - Strip & recover right
elevator. |
09/07/03 - Cover rudder & strip
out post lights for cleanup & repaint. |
|
09/20/03 - Locate & Drill Right
Horizontal Stabilizer & Elevator for Trim Cable. |
09/27/03 - Today, I hit the
300 HOUR MARK on my Coyote project, but it's taken NINE MONTHS.
;^) I also completed the rib rivet and tape covering portion for
the right side horizontal stabilizer, OFFICIALLY FINISHING ONE
PIECE...YAHOO!!!. |
09/28/03 - Edge tape left
horizontal stabilizer - second piece finished! |
|
10/05/03 - Finish edge tapes on
elevators & rudder. |
10/11/03 - Test KLX-135A GPS/COM
& KA-92 Antenna setup, prepare Flaps & Ailerons for fabric, trim Flap
Control Horns. |
10/18/03 - Cover both flap
structures, complete edge tape on one flap structure. |
|
10/19/03 - Cover both aileron
structures. |
10/25/03 - Finish edge tapes on
both ailerons and one flap. Receive wing and fuselage stands!!! |
10/26/03 - Setup wings for
covering. Relocate one door-up catch socket. |
|
10/31 - 11/02/03 - Drill and tap
wing-stand feet, clean right wing, remove wing hardware, apply
SuperFil to LE Wrap
areas, wet-sand SuperFil, pre-fit bottom fabric sheet to right wing. |
11/15/03 - WE HAVE HEAT IN THE
SHOP!!!! Reverse bolts in long wing channel. Cover bottom
of right wing. |
11/16/03 - Cover top of right
wing. |
|
11/22/03 - I have a hangar!!!
Continue fabric work on right wing. |
11/23/03 - Continue work on
right wing fabric. Install inspection rings, patches, rib rivet
top and bottom. |
11/24/03 - Begin and finish rib
taping top and bottom on right wing. Apply second coat of
adhesive on inspection, aileron and flap ring patches. |
|
11/28/03 - Apply root rib tapes,
apply edge tapes, begin final adhesive coat. |
11/29/03 - Complete right wing
fabric work! |
11/30/03 - Swap-out wings.
Prep left wing for covering, install new door-up catch socket, reverse
bolt orientation in aft long wing channels, apply SuperFil on leading
edge wrap. |
|
12/01/03 - Sand-out fill on
leading edge wrap, cover bottom of left wing. |
12/05/03 - Begin covering top
side of left wing. |
12/06/03 - Continue work on left
wing fabric, process to final shrink, apply inspection, exit rings and
patches. |
|
12/07/03 - Rib rivet top and
bottom of left wing. |
12/08 - 12/09/03 - Mark ribs for
rib tape top and bottom, apply initial bed of adhesive top & bottom,
apply rib tapes to bottom of left wing. |
12/13/03 - Apply tapes on
topside ribs, leading edge sides top and bottom and trailing edge. |
|
12/14 & 12/20/03 - Finish edge
tapes, apply adhesive over all required areas, cut & drill aileron &
flap exit covers. FINISHED WITH THE WING FABRIC! |
12/25/03 - Merry Christmas!
Swap out left wing for fuselage in stands, begin prepping fuselage for
covering, pre-fit KA-60 transponder antenna on ground plane. |
12/27/03 - Prep fuselage for
covering. Remove tailwheel spring & assembly, secure elevator
push-pull tube, control sticks and cables. Install longeron
fairings. Reorient bolts at S-3 lower pulleys. |
|
12/28/03 - Continue pre-covering
prep work on fuselage. Finish longeron fairings, install cable
inside housing and route trim cable assembly. |
12/29/03 - 01/02 - 01/03/04 -
Prep fuselage, sand-out transition tube fill, drill antenna ground
plane for COM and TXP Antennas, attach bottom fabric sheet to
fuselage. |
01/04/04 - 01/10/04 - Pre-fit
and apply fabric to left side of fuselage. |
|
01/16 - 01/17/04 - Prep fuse,
iron edges, pre-fit and apply fabric to right side of fuselage.
Shrink all fuselage fabric to final through three passes. |
01/21 - 01/23 - 01/24/04 - Prep
for edge tapes, rib rivet vertical stabilizer; run edge tapes on tail
section and transition tube. |
01/31/04 - Edge tapes on bottom
stringers and top right longeron. All patches cut and applied. |
|
02/06 - 02/07/04 - Tape top left
longeron, both side stringers, both bottom longerons, fwd formers, S3
top cross tube, apply bottom aft access ring and patch.. |
02/08/04 - Tape both door
frames, tape firewall, apply patches for horizontal stabilizer, drill
aft access panel. |
02/14 - 02/15/04 - Apply patches for
Elevator Yoke and Rudder Cable Exits and patch for Trim Cable Exit.
Thoroughly check and iron down all tape edges. Basic fabric work is
REALLY completed! |
|
02/28/04 - Replace gear, move
fuselage to paint shop. Begin panel item installation. |
02/29/04 - Continue work on
panel items |
03/01/04 - Continue work on
panel items |
|
03/03 - 03/05 - 03/06/04 - Visit
paint shop, work on panel items. |
03/07/04 - Double check all
remaining tape edges, MOVE FUSELAGE to the hangar!!! |
03/13/04 - Work at hangar; work
on panel |
|
03/14/04 - Just piddling
around...attach rudder and steering horns, rivet map box. |
03/20/04 - Piddling
again...finish cutouts on panel and sub-panel, finish map box size and
rivet. |
03/27/04 - Relocate home-shop to
hangar. |
|
03/28/04 - Move wings to hangar.
Move balance of 'shop stuff' from home shop to hangar. |
04/03/04 - Begin final assembly,
install main gear and fairings, wheels. Open aft access panel,
reattach elevator push pull tube, open inspection holes in left wing. |
04/04/04 - Continue final
assembly, install rudder cables, tailwheel and steering assembly. |
|
04/09 - 04/17/04 - Pick up
remaining painted items at shop, hang horizontal stabilizers, run trim
cable, hang elevators, install elevator horn and reattach to elevator
yoke, install fuel scuppers, attach aft baggage compartment door,
attach rudder stops, install rudder cable pulleys and keepers,
readjust steering chains to half-compression. |
04/24/04 - Install elevator yoke
covers and bottom aft cover, install all hinges for wings, ailerons
and flaps. Install aileron cable pulleys and control tee,
remove, grease and reinstall control stick torque tube assembly, rivet
right wing root closeout and begin final instrument panel fit. |
05/02 - 05/08/04 - Pick up and
deliver Rotax 912S to hangar, swap out wings on stands, open
inspection and control exit holes, replace fuel lines from lef tank
through root closeout, rivet left wing root closeout into place, hang
and mark doors for paint, finish final prefit for instrument panel, |
|
05/15 - 05/23/04 - Deliver doors
to paint shop, install Lighting package PS, install ELT & antenna,
install Transponder antenna. |
05/24/04 - Install COM Antenna &
Lighting assemblies. |
05/25/04 - Install hydraulic
brake lines and firewall hardware. |
|
05/27/04 - Attach flaps and
ailerons, attach control hardware, attach aileron push pull tube and
flap teleflex cable on right side. |
05/28/04 - Install gap seal on
left wing. |
06/05/04 - Work with panel
items, setup forward lift struts, prefit all strut attachment
hardware, attach wings and forward lift struts. |
|
06/12/04 - Pick up doors at
paint shop, hang doors & mask for stripes. Attach left side flap
and aileron control items, install aileron push-pull tube controls,
rig ailerons and flaps. Install balance of panel items, prefit
blind encoder, fabricate encoder attachment. |
06/19/04 - Pick up doors at
paint shop (this time with blue stripes applied!), prefit doors,
install door-up catches, install wing tip plugs, fabricate and install
brackets for avionics rack, install blind encoder, begin running
avionics wiring. |
07/31/04 - Finally back to work!
Re-install left flap horn, rig flaps properly, install aft lift
struts, clean hangar and Coyote! |
|
08/07/04 - Prefit left side flap
and aileron control closeouts, run wiring for avionics, etc. |
08/21/04 - Back to work!
Run PTT wiring and begin wiring for gauges, etc. |
08/28/04 - Apply silicone to PTT
wiring entering control sticks at base, solder PTT wiring to PTT
switches, install in Stick Closeout Caps, route and secure COM, GPS
and TXP antenna cabling. |
|
09/04/04 - Wiring again...
;^) |
09/11 - 09/18/04 - More
wiring... |
09/25/04 - Why yes, I'm still
working on the wiring... |
|
09/26/04 - Yep, more wiring, but
I'm closing in on the end of this part! |
10/02/04 - Finishing up the
wiring...not quite there yet, but CLOSE! ;^) |
10/03 - 10/08 - 10/09/04 -
Install solenoid, OAT wiring, Music Input, Battery Cables, Ground
Strobes & Power Ports, test Electrical System Components. |
|
10/16 - 10/23/04 - Test
Avionics, Fabricate and install Jury Struts. |
11/13/04 - Install & rig
elevator trim system. |
12/06/04 - Update on the recent
project delay... |
|
01/30/05 - Builder is still out of commission! |
07/09/05 -Finally back at the
hangar!!! Remove firewall, secure soundproofing material,
reinstall firewall, install gascolator, rivet firewall to Station 1. |
07/16/05 - Assemble radiator
mount and install radiator, radiator filler tee. Prefit engine
mount. |
|
07/24/05 - Install engine mount,
rectifier/regulator, test electrical and avionics. |
07/30/05 - Remove and reinstall
rectifier, install coolant recovery bottle, install engine. |
08/03 & 08/06/05 - Install 'S'
Coolant Hoses, Install Throttle and Choke Assemblies. |
|
|
|
|
|
08/13/05 - Install Oil Tank, Oil
Cooler and hoses. |
08/20/05 - Install hose clamps
on oil lines, remove radiator & mount, remove Choke Cable Clips, Drill
out rivets on heater closeout, install heater system components,
install exhaust system. |
08/27/05 - Install Fire Sleeve on
Oil Lines, install heater duct lines, attach propeller and begin
prefit on lower cowling. |
|
09/03/05 & 09/05/05 - Not a lot
of work accomplished over the holiday weekend, but I -did- wash the
Coyote and fly a little! |
09/10/05 - Lots of 'small stuff'
today. Run-out brake lines, trim Windshield Deck, Trim Choke
Cables, install grommets for Choke and Throttle Cables, install Fuel
Lines and Fire Sleeve. |
09/17/05 - Install Oil Pressure
Switch, finish-out fuel lines run including Fuel Shut Off Valve, Sump
Drain Assembly, install final wiring runs from panel for Ignition and
Starter. |
|
09/23 - 09/24/05 - Complete all
required engine to airframe wiring, secure oil tank to engine mount;
fill engine with oil, install battery and maintenance tender stub
wiring, begin final wiring for Fuel Flow System. |
10/15/05 - Back at work today
and finished with cooling system, all cables for throttle and choke
system are in place and secure. |
10/22/05 - Fill coolant system,
complete install on Parking Brake, begin filling brake system, RUN
ENGINE for first time! |
|
02/10/06 - Where's the builder been???? |
04/15/06 - Sometime back in
January, I bled the brake system and on 04/15, I finally got back to
work! Cut, fit and install Spinner. |
04/22/06 - Prefit cowling,
trim, adjust, trim, you get the picture... |
|
04/29/06 - More work on the
cowling... |
05/06/06 - And yet more cowling
work... |
|
|
|
|
|