Building the S6S...

Daily progress sheets are linked below by date.  Please feel free to comment on the construction and assembly process.  I can use all the help I can get!

790.5 Hours to date.  Timesheet detail links below ('Calendar Year 200X')  - Note these are LARGE files!

Calendar Year 2002  Calendar Year 2003  Calendar Year 2004  Calendar Year 2005  Calendar Year 2006

12/11/02 - First day in the shop 12/12/02 - Inventory Begins! 12/14/02 - Parts Count...part 2
12/21/02 - Inventory finished, building begins! 12/28/02 & 12/29/02 - Assembling floorboard components 01/01/03 - Pre-fit, drill and cleco firewall and cowl mounting brackets.  Drill upper engine mount.
01/03/03 - Fit, clamp, drill & rivet right side fwd contour former 01/04/03 - Fit, clamp, drill & rivet left side fwd contour former and begin work on control stick assembly 01/05/03 - Complete control stick assembly installation, assemble and install Aileron Cable assembly
01/08/03 - Fabricate stops & bushings, assemble and install Elevator Push-Pull Tube Assembly 01/15/03 - Begin trim and fit interior sections (Ugh! - Well at first, but all's well that ends well!) 01/18/03 - Complete interior pre-fit, start seat construction and assembly
02/04/03 - Finally back to work! Complete first seat and begin installing covers 02/08/03 - Complete seat #1 covering, assemble seat #2 02/09/03 - Finish assy/cover 2nd  seat. Pre-fit finished, remove seats & interior, various minor items fixed.
02/15/03 - Assembled and installed the GEAR!  Yes, of course I sat in it! 02/22/03 - Cut and fit windshield deck, panel top covers, pre-fit panel. 02/23/03 - Completed panel top closeouts and final pre-fit instrument panel.
03/01/03 - Built gear-jig, pre-fit, drilled and installed main gearlegs. Built traveler for moving fuse in-shop. 03/08/03 - Fit, drill and cut axles, finish cut windshield deck. 03/12/03 - Remove panel top closeouts, remove wheels and main gear, reinstall windshield deck, initial layout, drill and cleco windshield to S2 tabs.
03/15/03 - Finish trim deck, fit, drill and trim windshield, reinstall gear and wheels. 03/16 - 03/17 - 03/22/03 - Working on door construction and assembly. 03/23/03 - Finish trim right side door window.  Fit, trim, drill, cleco and reinstall left side door/window assembly.
03/24/03 - Fabricate & install battery box. 03/29/03 - Install Aft Baggage Compartment, drill & cleco frame, etc. 04/02 - 04/05/03 - Working on right side  replacement bubble door installation.
04/11 - 04/12/03 - Working on left side replacement bubble door installation. 04/13/03 - Finished left side door assembly and completed the first phase of my project!!! 04/14/03 - Begin work on vertical stabilizer.
04/16/03 - Fabricate patch for aft baggage compartment frame, drill door and install quick locks, hang rudder. 04/17/03 - Finish aft baggage compartment frame, rivet door hinges.  Construct left & right horizontal stabilizers. 04/18/03 - Install compression ribs in horizontal stabilizers, install hardware on elevators and attach all to tail group.
04/19/03 - Install rudder cap, rudder horns and hardware, fabricate and install trim tab. 04/20/03 - Happy Easter! - Installed cables on tail group, installed elevator push/pull tube and yoke, second phase of project nearly complete!!! 04/21/03 - Adjust elevator up/down position and installed elevator stops.
04/26/03 - Install doubler in bottom rudder tube, assemble hardware on flaps & ailerons. 05/03 - 05/06/03 - Rearrange workspace, pull parts for wing construction. 05/08 - 05/10/03 - Begin work on wings, install hardware up to flap/aileron hinges.
05/11/03 - Install flap & aileron hinges, install internal bracing tubes on RH wing structure. 05/14 - 05/17/03 - Install internal brace tubes, left wing.  Install Aileron Push Pull Tube guides, L&R, Flap Teleflex Retainer L&R, Aileron Bell Crank Gusset and Aileron Bell Crank L&R, L&R Wing Tip Bows. 05/21 -22 - 05/23/03 - Working on fuel tanks, pull parts, drill holes, install fittings, perform air test.
05/24/03 - Water test fuel tanks, empty & clean tanks.  Install tank support tubes and hardware, install left side tank. 05/25 - 05/26/03 - Drill & cleco rib clips (fore & aft) on right side wing structure. 05/27 - 28 - 29 - 05/31/03 - Drill & cleco fore & aft rib clips on left wing structure.  Drill & cleco all topside ribs on left wing structure. - OUT OF CLECOS!
06/07/03 - Drill & cleco all remaining top and bottom ribs in Left and Right Wing structures. - OUT OF CLECOS AGAIN! 06/14/03 - Drill & cleco root rib skin and trim, drill & rivet rib channels for right side wing structure. 06/28/03 - Trim, drill, install rib channels in right side wing structure.
06/29/03 - Drill & rivet rib clips on right side wing structure. 07/02/03 - Finish drill & rivet rib clips, rivet ribs to spars on right side wing structure. 07/04 - 07/05/03 - Install rib channels, drill & rivet rib ends and clips, install leading edge wrap on left side wing structure.
07/12/03 - Install leading edge wrap and topside root skin on right side wing structure. 07/13/03 - Rivet topside root skin, drill & cleco fuel scupper.  Trim, tension, drill & cleco left side leading edge wrap. 07/16 - 07/19/03 - Install top and bottom root skins on left wing, epoxy-bond bottom side skin, begin installation for antenna ground plane.
07/20/03 - Install bottom root skin on right wing, drill, rivet & epoxy-bond.  Install antenna mount plate. 07/23 - 07/26/03 - Bond AND rebond top aft skin on right wing, install braces on left wing from rib 6 through 9, drill for pitot & static tubes. 08/02/03 - Remove root rib skins, cut left wing fuel tank neck to height, install Pitot & Static tubes and lines, install left wing Nav/Strobe mount and wiring.
08/03/03 - Right wing structure, trim fuel tank neck to height, install wiring and tip mount for Nav/Strobe kit, drill 5 ribs topside. 08/4 - 08/09/03 - Finish drill & debur top & bottom ribs on right wing.  Drill & debur all ribs on left wing.  Install ends in aileron push pull tubes.  Install main push pull tube in left wing.  Fabricate and install flap lever assembly, flap teleflex cable & retainers, pre-install flap teleflex cable in left wing. 08/16/03 - Visited Rans factory for the first time and ordered my kit ONE YEAR AGO TODAY! :^)  Rebonded left top aft and right bottom aft root wing skins today - no fabric work today. :^(
08/17/03 - Rivet LE Wrap L&R, cut fabric for wings, remove tail section components for covering. 08/23/03 - Fabric Covering Phase Begins!!!  Left horizontal stabilizer completed. 08/30/03 - Cover right horizontal stabilizer, cut fabric for elevators, rudder and one flap.
08/31/03 - Cover left & right elevators. 09/06/03 - Strip & recover right elevator. 09/07/03 - Cover rudder & strip out post lights for cleanup & repaint.
09/20/03 - Locate & Drill Right Horizontal Stabilizer & Elevator for Trim Cable. 09/27/03 - Today, I hit the 300 HOUR MARK on my Coyote project, but it's taken NINE MONTHS.  ;^)  I also completed the rib rivet and tape covering portion for the right side horizontal stabilizer, OFFICIALLY FINISHING ONE PIECE...YAHOO!!!. 09/28/03 - Edge tape left horizontal stabilizer - second piece finished!
10/05/03 - Finish edge tapes on elevators & rudder. 10/11/03 - Test KLX-135A GPS/COM & KA-92 Antenna setup, prepare Flaps & Ailerons for fabric, trim Flap Control Horns. 10/18/03 - Cover both flap structures, complete edge tape on one flap structure.
10/19/03 - Cover both aileron structures. 10/25/03 - Finish edge tapes on both ailerons and one flap. Receive wing and fuselage stands!!! 10/26/03 - Setup wings for covering.  Relocate one door-up catch socket.
10/31 - 11/02/03 - Drill and tap wing-stand feet, clean right wing, remove wing hardware, apply SuperFil to LE Wrap areas, wet-sand SuperFil, pre-fit bottom fabric sheet to right wing. 11/15/03 - WE HAVE HEAT IN THE SHOP!!!!  Reverse bolts in long wing channel.  Cover bottom of right wing. 11/16/03 - Cover top of right wing.
11/22/03 - I have a hangar!!!  Continue fabric work on right wing. 11/23/03 - Continue work on right wing fabric.  Install inspection rings, patches, rib rivet top and bottom. 11/24/03 - Begin and finish rib taping top and bottom on right wing.  Apply second coat of adhesive on inspection, aileron and flap ring patches.
11/28/03 - Apply root rib tapes, apply edge tapes, begin final adhesive coat. 11/29/03 - Complete right wing fabric work! 11/30/03 - Swap-out wings.  Prep left wing for covering, install new door-up catch socket, reverse bolt orientation in aft long wing channels, apply SuperFil on leading edge wrap.
12/01/03 - Sand-out fill on leading edge wrap, cover bottom of left wing. 12/05/03 - Begin covering top side of left wing. 12/06/03 - Continue work on left wing fabric, process to final shrink, apply inspection, exit rings and patches.
12/07/03 - Rib rivet top and bottom of left wing. 12/08 - 12/09/03 - Mark ribs for rib tape top and bottom, apply initial bed of adhesive top & bottom, apply rib tapes to bottom of left wing. 12/13/03 - Apply tapes on topside ribs, leading edge sides top and bottom and trailing edge.
12/14 & 12/20/03 - Finish edge tapes, apply adhesive over all required areas, cut & drill aileron & flap exit covers.  FINISHED WITH THE WING FABRIC! 12/25/03 - Merry Christmas!  Swap out left wing for fuselage in stands, begin prepping fuselage for covering, pre-fit KA-60 transponder antenna on ground plane. 12/27/03 - Prep fuselage for covering.  Remove tailwheel spring & assembly, secure elevator push-pull tube, control sticks and cables.  Install longeron fairings. Reorient bolts at S-3 lower pulleys.
12/28/03 - Continue pre-covering prep work on fuselage.  Finish longeron fairings, install cable inside housing and route trim cable assembly. 12/29/03 - 01/02 - 01/03/04 - Prep fuselage, sand-out transition tube fill, drill antenna ground plane for COM and TXP Antennas, attach bottom fabric sheet to fuselage. 01/04/04 - 01/10/04 - Pre-fit and apply fabric to left side of fuselage.
01/16 - 01/17/04 - Prep fuse, iron edges, pre-fit and apply fabric to right side of fuselage.  Shrink all fuselage fabric to final through three passes. 01/21 - 01/23 - 01/24/04 - Prep for edge tapes, rib rivet vertical stabilizer; run edge tapes on tail section and transition tube. 01/31/04 - Edge tapes on bottom stringers and top right longeron.  All patches cut and applied.
02/06 - 02/07/04 - Tape top left longeron, both side stringers, both bottom longerons, fwd formers, S3 top cross tube, apply bottom aft access ring and patch.. 02/08/04 - Tape both door frames, tape firewall, apply patches for horizontal stabilizer, drill aft access panel. 02/14 - 02/15/04 - Apply patches for Elevator Yoke and Rudder Cable Exits and patch for Trim Cable Exit.  Thoroughly check and iron down all tape edges. Basic fabric work is REALLY completed!
02/28/04 - Replace gear, move fuselage to paint shop.  Begin panel item installation. 02/29/04 - Continue work on panel items 03/01/04 - Continue work on panel items
03/03 - 03/05 - 03/06/04 - Visit paint shop, work on panel items. 03/07/04 - Double check all remaining tape edges, MOVE FUSELAGE to the hangar!!! 03/13/04 - Work at hangar; work on panel
03/14/04 - Just piddling around...attach rudder and steering horns, rivet map box. 03/20/04 - Piddling again...finish cutouts on panel and sub-panel, finish map box size and rivet. 03/27/04 - Relocate home-shop to hangar.
03/28/04 - Move wings to hangar.  Move balance of 'shop stuff' from home shop to hangar. 04/03/04 - Begin final assembly, install main gear and fairings, wheels.  Open aft access panel, reattach elevator push pull tube, open inspection holes in left wing. 04/04/04 - Continue final assembly, install rudder cables, tailwheel and steering assembly.
04/09 - 04/17/04 - Pick up remaining painted items at shop, hang horizontal stabilizers, run trim cable, hang elevators, install elevator horn and reattach to elevator yoke, install fuel scuppers, attach aft baggage compartment door, attach rudder stops, install rudder cable pulleys and keepers, readjust steering chains to half-compression. 04/24/04 - Install elevator yoke covers and bottom aft cover, install all hinges for wings, ailerons and flaps.  Install aileron cable pulleys and control tee, remove, grease and reinstall control stick torque tube assembly, rivet right wing root closeout and begin final instrument panel fit. 05/02 - 05/08/04 - Pick up and deliver Rotax 912S to hangar, swap out wings on stands, open inspection and control exit holes, replace fuel lines from lef tank through root closeout, rivet left wing root closeout into place, hang and mark doors for paint, finish final prefit for instrument panel,
05/15 - 05/23/04 - Deliver doors to paint shop, install Lighting package PS, install ELT & antenna, install Transponder antenna. 05/24/04 - Install COM Antenna & Lighting assemblies. 05/25/04 - Install hydraulic brake lines and firewall hardware.
05/27/04 - Attach flaps and ailerons, attach control hardware, attach aileron push pull tube and flap teleflex cable on right side. 05/28/04 - Install gap seal on left wing. 06/05/04 - Work with panel items, setup forward lift struts, prefit all strut attachment hardware, attach wings and forward lift struts. 
06/12/04 - Pick up doors at paint shop, hang doors & mask for stripes.  Attach left side flap and aileron control items, install aileron push-pull tube controls, rig ailerons and flaps.  Install balance of panel items, prefit blind encoder, fabricate encoder attachment. 06/19/04 - Pick up doors at paint shop (this time with blue stripes applied!), prefit doors, install door-up catches, install wing tip plugs, fabricate and install brackets for avionics rack, install blind encoder, begin running avionics wiring. 07/31/04 - Finally back to work!  Re-install left flap horn, rig flaps properly, install aft lift struts, clean hangar and Coyote!
08/07/04 - Prefit left side flap and aileron control closeouts, run wiring for avionics, etc. 08/21/04 - Back to work!  Run PTT wiring and begin wiring for gauges, etc. 08/28/04 - Apply silicone to PTT wiring entering control sticks at base, solder PTT wiring to PTT switches, install in Stick Closeout Caps, route and secure COM, GPS and TXP antenna cabling.
09/04/04 - Wiring again...  ;^) 09/11 - 09/18/04 - More wiring... 09/25/04 - Why yes, I'm still working on the wiring...
09/26/04 - Yep, more wiring, but I'm closing in on the end of this part! 10/02/04 - Finishing up the wiring...not quite there yet, but CLOSE!  ;^) 10/03 - 10/08 - 10/09/04 - Install solenoid, OAT wiring, Music Input, Battery Cables, Ground Strobes & Power Ports, test Electrical System Components.
10/16 - 10/23/04 - Test Avionics, Fabricate and install Jury Struts. 11/13/04 - Install & rig elevator trim system. 12/06/04 - Update on the recent project delay...
01/30/05 - Builder is still out of commission!  07/09/05 -Finally back at the hangar!!!  Remove firewall, secure soundproofing material, reinstall firewall, install gascolator, rivet firewall to Station 1. 07/16/05 - Assemble radiator mount and install radiator, radiator filler tee.  Prefit engine mount.
07/24/05 - Install engine mount, rectifier/regulator, test electrical and avionics. 07/30/05 - Remove and reinstall rectifier, install coolant recovery bottle, install engine. 08/03 & 08/06/05 - Install 'S' Coolant Hoses, Install Throttle and Choke Assemblies.
     
08/13/05 - Install Oil Tank, Oil Cooler and hoses. 08/20/05 - Install hose clamps on oil lines, remove radiator & mount, remove Choke Cable Clips, Drill out rivets on heater closeout, install heater system components, install exhaust system. 08/27/05 - Install Fire Sleeve on Oil Lines, install heater duct lines, attach propeller and begin prefit on lower cowling.
09/03/05 & 09/05/05 - Not a lot of work accomplished over the holiday weekend, but I -did- wash the Coyote and fly a little! 09/10/05 - Lots of 'small stuff' today.  Run-out brake lines, trim Windshield Deck, Trim Choke Cables, install grommets for Choke and Throttle Cables, install Fuel Lines and Fire Sleeve. 09/17/05 - Install Oil Pressure Switch, finish-out fuel lines run including Fuel Shut Off Valve, Sump Drain Assembly, install final wiring runs from panel for Ignition and Starter.
09/23 - 09/24/05 - Complete all required engine to airframe wiring, secure oil tank to engine mount; fill engine with oil, install battery and maintenance tender stub wiring, begin final wiring for Fuel Flow System. 10/15/05 - Back at work today and finished with cooling system, all cables for throttle and choke system are in place and secure. 10/22/05 - Fill coolant system, complete install on Parking Brake, begin filling brake system, RUN ENGINE for first time!
02/10/06 - Where's the builder been???? 04/15/06 - Sometime back in January, I bled the brake system and on 04/15, I finally got back to work! Cut, fit and install Spinner. 04/22/06 - Prefit cowling, trim, adjust, trim, you get the picture...
04/29/06 - More work on the cowling... 05/06/06 - And yet more cowling work...  
     

Back

Last Update: 05/06/2006